PERT Calculator

Calculate the PERT expected duration, standard deviation and variance from three project estimates, or use a triangular average.

Result
—

How to calculate

Add the optimistic duration, four times the most likely duration and the pessimistic duration. Divide by six for the PERT weighted duration. Divide the high to low spread by six for the conventional standard deviation estimate, then square it for variance. The triangular estimate gives each input equal weight.

Worked example

Use Three point estimate method PERT weighted estimate · Optimistic duration 4 · Most likely duration 7 · Pessimistic duration 16 · Duration unit days. The result is ≈ 8 days.

Input and result notes

Use optimistic ≤ most likely ≤ pessimistic. Review uncertain project schedules by considering task relationships and correlated risks.