High-Low Method Calculator

Estimate fixed and variable costs from the highest and lowest activity points using the high low method.

Result
—

How to calculate

Calculate the change in total cost per additional unit of activity, then subtract variable cost from either observed total. Use the resulting fixed and variable estimates to forecast cost.

Worked example

Use Lowest activity volume 100 · Total cost at low activity (USD) 2200 · Highest activity volume 300 · Total cost at high activity (USD) 4600 · Forecast activity volume 200. The result is 1000.00 USD.

Input and result notes

Enter numbers using the same units. Rounded results are marked with ≈.